Fwd: BioE+ChE Construction Update - Week of April 16th



Please find attached the update for next week. 

 

Changes from last week include: 

  • Shotcrete operations will resume work on the North side of the site in the light well.
  • East portions of slab on grade in the basement and subbasement are now being poured next week.
  • Major pours next week will be for slab on grade on Monday (approx. 9 trucks) and Friday (approx. 15 trucks).

Have a great weekend.

  