Hi all --
Two steps forward, one step back...
STSetch2: Delivery on the repaired and updated RF generator was
delayed. It arrived Wednesday and so was installed yesterday. Elmer
and Jim have been working on it since --there appears to be a
communication problem between it and the STS system. There are some
clues that Elmer will follow up on with both STS and MKS (who service
the generator) on Monday. If these don't pan out quickly, Elmer has a
lead on an immediately available, STS-warranted replacement generator,
He has also arranged to have STS send the first-available field service
engineer, tentatively next week.
Lampoly: The faulty generator was repaired, calibrated, and shipped by
FedEx today (shipping was delayed, as we'd hoped it would arrive
today.) It will arrive Monday. Installation and functional testing
should be fairly quick.
The gang is also working on ensuring that the repairable spares we have
are documented and sent out for service as needed, so we will not be
nailed by lack of a functional spare generator.
Again, thanks for your patience --
Team Etch