McGwire-Hester will be doing some more demolition (AKA jack hammering)
this morning from about 7:30 to 10 a.m. along Via Pueblo. This may
affect vibration-sensitive activities in the lab.
The site supervisor believes that this should complete most of the
activity that creates significant vibration until they start compaction
later in the construction process.