Please find attached the update for next week.
Changes from last week include:
- Shotcrete operations will resume work on the North side of the site in the light well.
- East portions of slab on grade in the basement and subbasement are now being poured next week.
- Major pours next week will be for slab on grade on Monday (approx. 9 trucks) and Friday (approx. 15 trucks).
Have a great weekend.